PRHS's $36 Million Expansion/Renovation Project Coming in Under Budget

The Pine-Richland High School project is estimated to cost about $216,000 less than expected.

Nearly all the bills have been paid for the $35.9 million expansion/renovation project for Pine-Richland High School and the projected final tally shows the project will come in at about $216,000 under budget.

That is what Assistant Finance Director Ryan Manzer told the Pine-Richland School Board on Monday night.

The numbers reflect savings on financing costs and furniture plus the remaining construction contingency, according to documents provided to the board.

Find out what's happening in Pine-Richlandwith free, real-time updates from Patch.

Here is a summary of overall costs. For more details, click on the PDF of project costs in the photo box to the right.

 

Find out what's happening in Pine-Richlandwith free, real-time updates from Patch.

PRHS EXPANSION PROJECT Original  Projected Projected as of 12/31/2012 Budget Costs Variance Financing      $702,653       $411,918     290,735 Pre-Construction / Construction   $3,698,444    $4,266,666    (568,222) Construction $26,788,649  $27,939,409 (1,150,760) Insurance      $692,085      $721,461      (29,376) Other Expenditures   $2,714,587   $2,380,491     334,096 Construction Contingency   $1,339,432  1,339,432 Total Costs $35,935,850 $35,719,945     215,906

 

__________________________

Please help us get to 1,000 Facebook “likes” by clicking here and “liking” us.

Check out some of today's other top stories here.

 


Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.

We’ve removed the ability to reply as we work to make improvements. Learn more here

More from Pine-Richland